Summary

Sylvan Township residents Norman and JoAnn Weber said the Road Commission is secretly widening their two-lane country road and cutting trees without justification; Maciejewski credited their advocacy for scaling the project back.

At a glance

Total mentions
8
Last 30 days
0

Last discussed Apr 15, 2026.

Impact analysis

💰Financial impact

The roughly $600,000 project is taxpayer-funded; removal of a mature oak can cost up to $15,000 per tree.

✅Who benefits

Werkner Road residents who pressed for a revised, less disruptive plan.

⚠️Who could be affected

Residents whose mature trees were removed and who fear a wider road will invite speeding and truck traffic.

Mentions & discussions (8)

MeetingApr 15, 2026

Board of Commissioners Working Session - Apr 15, 2026

Chair Katie Scott pressed the Road Commission to hold evening meetings with public comment, saying the 1 p.m. weekday schedule makes it hard for residents — and even commissioners — to participate.

MeetingApr 15, 2026approved

Board of Commissioners - Apr 15, 2026

Sylvan Township residents Norman and JoAnn Weber said the Road Commission is secretly widening their two-lane country road and cutting trees without justification; Maciejewski credited their advocacy for scaling the project back.

MeetingMar 4, 2026

Board of Commissioners Working Session - Mar 4, 2026

Commissioners challenged the Road Commission's removal of 42 trees for the millage-funded Workner Road project, questioning whether drainage demands really require clearing trees and pressing for policy changes modeled on Charleston County, South Carolina's approach.

MeetingMar 4, 2026

Board of Commissioners - Mar 4, 2026

The road commission is cutting 42 trees for the Sylvan Township resurfacing project — mostly small trees, but commissioners Hodge, Rabhi and Scott pushed hard on drainage, flooding and whether the tree policy should protect 'grand trees' like Charleston County does.

MeetingFeb 18, 2026

Board of Commissioners - Feb 18, 2026

Several residents criticized the Road Commission, including tree removal on the Werkner Road project in Sylvan Township. Commissioners acknowledged the concerns.

MeetingFeb 4, 2026

Board of Commissioners - Feb 4, 2026

Sylvan and Webster Township residents pleaded with the board to stop the Road Commission's Werkner Road widening, which threatens 150-300-year-old oak and hickory trees. Commissioners acknowledged frustration; a Road Commission public hearing is set for next Tuesday.

MeetingJan 21, 2026

Board of Commissioners - Jan 21, 2026

Residents blasted the Road Commission for cutting mature trees and for a Werkner Road widening project they say lacks safety justification or environmental review. A petition has over 1,300 signatures; public hearings are set for February 9 and 11.

MeetingJan 7, 2026

Board of Commissioners - Jan 7, 2026

A Chelsea resident, citing 700-plus petition signatures, urged the board to tell the Road Commission to repair Werkner Road without widening it, saying the widening threatens century-old trees, private land, and safety data shows only five deer-related crashes in four years. Two public meetings are set for February 9 and 11.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Washtenaw County

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.